Completed Projects

1. Technopromexport (TPE)

 Customs clearance and transportation of Ghorashal Power Station cargoes from Chittagong port to plant site at Ghorashal.

2. Sinha Peoples Energy Limited

52.50 MW Power Plant – Kathpatti, Munshiganj

Delivered 7 (seven) Nos. of STX Engines, each 182 MT in weight along with full specification of the power plant machinery, to the island of Kathpatti, Munshigsnj. A channel of 1.5 Km had to be dredged to bring the barges to the Power Plant.

3. Bibiyana 450 MW Combined Cycle Power Plant

Summit Bibiyana II Power Co., Ltd.

Customs clearance and transportation of 30,000 FRT of project cargoes from Mongla/Chittagong port to Sherpur, Bibiyana. Cargo includes 188 MT TFX among others.

4. Kodda 150 MW Dual Fuel Power Plant

BPDB-RPCL Powergen LTD., – CCC Engineering Ltd.

Customs cleared and transported 9 x 325 MT MAN Engines, Alternators and complete power plant equipment from Mongla and Chittagong port to Kodda site. Had to construct a special cofferdam of 900ft x 250ft to reduce water level in the Turag river for smooth passage of the barges under Ashulia bridge.

5. Shahjibazar 330 MW Combined Cycle Power Plant

Bangladesh Power Development Board

Customs clearance, inland transportation of entire project cargoes comprising of heavy lifts as well as general cargoes from Chittagong and Mongla port to Shahjibazar Power Plant site. Building of by-pass road and bridge on the Khoai River and construction of temporary jetty at Sherpur, Moulvibazar. This project is on going now (June, 2015)

6. Payra 1320 MW Thermal Power Plant

Bangladesh China Power Company (Pvt.) Ltd.

A Concern of:North West power Generation Co., Ltd. and China National Machinery Import & Export Corporation (CMC). Customs clearance and Transportation of 1st Consignment Comprising of 424 pages/1,289.293 MT/3,083.45 CBM cargoes by barge from Chittagong port to Payra Power Plant jetty. These cargoes were received directly from the Vessel onto the flat barges.

7. Bhola 225 MW Power Plant~A project of Notun Biddyut (Bangladesh) Ltd.

Contrsctor: Bishu Infra – 2018.

We constructed a heavy duty jetty on the bank of Tetulia river to handle both heavy lifts and cranage operations during high and low tide.

8. Mirsarai 150 MW Dual Fuel Power Plant: A project of BR Powergen Limited

Contractor: Sinohydro Corporation Ltd. – 2019.

We got the contract for clearance and transportation of 240 units of 40′ containers from Chattogram port to Mirsarai Power Plant project. We have started delivery of the containers very recently.

9. Sirajganj 413 MW Power Plant

The temporary landing jetty was constructed by Avant logistics Ltd. at Sirajganj for receiving 3 Heavy Lift cargos and General cargos for the construction of 413 MW Dual Fuel CCPP. The Heavy Lifts were GT-410 Ton, GTG-330 Ton and TFX- 210 Ton.

10. Ruppur 2,400 MW Nuclear Power Plant

Contractor: Atomstroyexport, Russia – since 2017, ongoing

Avant logistics Ltd. started delivering cargoes to Ruppur Nuclear Power Plant (RNPP) from the beginning of 2018. Till now Avant has delivered over 40,000 FRT of cargoes through Chattogram port, Mongla port and Dhaka Airport. The highest load of a single piece so far was 465 Ton (Stator).Avant delivered two such Stators. We used specially constructed barges, jetties and super cranes for unloading of the heavy lift cargoes and used 24 lines of SPMT for transportations of these heavy lifts. Avant plans to handle more specially designed cargoes comprising of heavy lifts, ODC and general cargoes for RNPP project in coming days. Avant has worked for ORGANOGOSTROY in the earlier days and now working for other major sub-contractors of ATOMSTROYEXPORT (ASE) at RNPP project.

11. Summit Meghnaghat 583 MW Power Plant - Phase II

Contractor: General Electric (GE) & NEPC – since 2019-2023

Customs clearance and transportation of full specifications (70,000 FRT or more) of this project, which includes twenty three units of Heavy Lifts consisting of Gas Turbines (378 MT), Generators (307 MT) & Transformers (320 MT) as well as Break-bulk, General Cargoes and Containers for the entire project. All HRSG Modules and 378 MT Gas Turbine and 292 MT Generator were delivered to Meghnaghat site. 35,000 FRT cargoes are yet to arrive. 

12. Ghorashal Polash Urea Fertilizer Factory (GPUFF)

Contractor: Mitsubishi heavy Industries Ltd. – since 2020, ongoing

Avant Logistics Ltd. signed a contract with COSCO Shipping Project Logistics, China for the construction of specially designed jetty at Ghorashal for unloading the entire project materials (600,000 FRT approx.) comprising of super heavy lifts, ODCs and general cargoes to be imported for this project. Construction started in February 2021 and was completed in July, 2021. Cargoes are due from May 2021. Avant also signed a contract for customs clearance, transportation for the above cargoes from Chattogram port, Mongla port and Dhaka airport.

13. Rohanpur 400/132 KV interim Sub-station

Contractor: Reverie Power & Automation Engineering Ltd. – 2022-2023

Avant Logistics Ltd. signed a contract with Reverie Power & Automation Engineering Ltd. for delivery of 3 (three) nos. Transformers to Rohanpur, Rangpur, Bogra & Gopalganj each weighting 322 MT. Avant Logistics Ltd. will undertake barging and long haulage (200 km) to deliver these Transformation including construction of jetty, negotiating sharp turnings and widening of 10 km road. Avant Logistics Ltd. is negotiating with Reverie for delivery similar cargoes for Bogra and Gopalganj Sun-station.

Avant logistics Ltd. signed a contract with Reverie Power & Automation Engineering Ltd. for delivery of 3(three) nos Transformers (TFX) each weighing 322 MT to be delivered to Rohanpur, Chapainawabganj. The first TFX was delivered in March,2022 and Two others were delivered during February – March,2023. It was an extremely challenging job involving construction of jetty at Mukterpur, Rajshahi on the bank of Padma River and barging from Mongla to Mukterpur in dry season. The TFXs were ­­then transferred from barges to Multi Modulus Axles (HMT). We used 14 lines of HMT to transport the TFXs through 110 km road where some part of road was under construction. We delivered all TFXs safely and placed them of the foundations including alignments.

14. SREEPUR 150 +/- 10 PCT ( HFO BASED) POWER PLANT

A Project of  B-R Powergen Ltd.

Contractor: MAX INFRASTRUCTURE LIMITED -2023

 

Avant Logistics received 9 (nine) sets of equipment consisting of MAN Engines, each 325 MT (dim 13.0mx4.9mx6.5m), Alternators, each 62 MT (dim 4.68mx5.5mX5.5m) and Turbo Chargers, each 32 MT ( dim 5.2mx3.6mx3.6m) at Mongla port in one single shipment. After Customs and port clearance all 27 pcs were loaded onto 11 (eleven) flat top barges. The barges were chosen very carefully with strong deck but low draft as we had to negotiate narrow river after Ghorashal in the months 0f Feb-March. We constructed a jetty at Sreepur on the bank of Sitalakhya river and transferred all cargoes to the jetty for onward transfer to respective foundations about 700m far, We also did placement and alignment of all cargoes. For this job we used the equipment and manpower:

                      Flat top barges              –    11 nos

                             Hydraulic winches          –    2000 ton X 1

                                                                  –    800 ton X 2

                            Cranes                         –    230 tonX1

                                                                  –    170 ton X 1

                            Low bed trailers            –    150 ton X 3

                            Manpower                     –    150 people

The project was completed successfully and on times. Avant Logistics Ltd received special bonus for this project from the client, Max Infrastructure Limited.